Completed in just 30 days
Year: 1998
Location: Kolavai Lake near paranur Toll Gate (Chengalpattu)
Specifications: 6.1 m X 6 span
Achievement: Honoured for completed the work in 30 days.
Meter Gauge to Broad Gauge conversion and Fort railway station modification
Year: 2002
Location: Egmore to Beach Railway station(II Reach)
Achievement: Completed in just 45 days.
Meter Gauge to Broad Gauge conversion
Year: 2004
Location: Saidapet to Nungambakkam
Achievement: Modification done within 4 months of time
Designed and Executed
Year: 2001
Location: Pazavanthangal to Nelson Manickam Road Subway
Specifications: 35 cm thick, 7.5 m to 18.5 m span (Various Span)
Achievement:
1st thinnest slab in southern railways
Pazavanthangal subway
Aranganathar subway
Madly subway
Duraiswamy subway
Nelson Manickam Road Subway
Location:Thozupedu (Road Order Bridge) Near Acharapakkam
Year: 2005
Challenge Faced: 90 Degree sque span, PSC Gurder (27 m span)
Location:Vandaloor Road Over Bridge
Year: 2012
Specifications: 90 degree Sque, Steel Gurder, Composite Gurder
Super structure - RCC Structure
Mainspan - Composite Gurder
2 types of Foundation
Main Foundation: Raft foundation and Well foundation
Year: 2009 - 2010
Location:Thambaram to Egmore
Challenge Faced: Only Night Work (12 - 04)
Year: 2006
Location: Thuruindriyur railway station and pattabiram railway station
Specifications: Pile Foundation with 1m dia